How to Measure and Shorten Order Delivery Time: A Course on Confirmation, Preparation, Handoff, and Transit

How do you measure and shorten order delivery time? Four stages, average and 90th-percentile time, on-target delivery rate, the impact of delays, and a reduction plan with a worked calculation.

Contents 14 sections
  1. What will you be able to do by the end of this training?
  2. Lesson 1: Why is average delivery time not enough on its own?
  3. Lesson 2: What four stages make up the time from order to delivery?
  4. Lesson 3: How do you measure stage times?
  5. Lesson 4: How do you calculate average and 90th-percentile delivery time?
  6. Lesson 5: How do you calculate the on-target delivery rate?
  7. Lesson 6: How do late deliveries affect complaints and returns?
  8. Lesson 7: How do you find the bottleneck in delivery time?
  9. Lesson 8: How do you prepare a plan to shorten delivery time?
  10. What are the most common mistakes in measuring order delivery time?
  11. How does NetKasam make delivery time tracking easier?
  12. Mini quiz: Test what you have learned
  13. Conclusion: Manage delivery time in stages, not as a single number
  14. Frequently Asked Questions About Order Delivery Time

The customer starts the clock the moment they place the order. For you, the process is divided into stages like "confirmation, packing, shipping"; for the customer, there is a single wait: when will the package arrive at my door. Businesses often summarize this wait with a single "average of 4 days" figure, yet that figure does not tell you which stage lost time, how many orders broke your promise, or how long the latest-arriving orders waited.

This post is an 8-lesson hands-on course. We will answer the question how do you measure and shorten order delivery time using a sample e-commerce business with 1,000 orders a month: four stages, measurement with timestamps, the difference between average and 90th-percentile time, the on-target delivery rate, the impact of delays on complaints and returns, finding the bottleneck, and a shortening plan. At the end there is a mini quiz with an answer key. All figures are sample values chosen to demonstrate the method; use your own order records.

What will you be able to do by the end of this training?

In short: You will split the time from order to delivery into stages, calculate the average and 90th-percentile time, find the on-target rate, estimate the cost of delay, and set a shortening target for the largest bottleneck.

Course mapThe six steps of the order delivery time study
  1. 01
    SplitSeparate the time into confirmation, preparation, handoff, and transit.
  2. 02
    MeasureWrite each stage's start and end time on the order.
  3. 03
    SummarizeProduce the average, the 90th-percentile time, and the longest time.
  4. 04
    RateFind the percentage of orders delivered within the target.
  5. 05
    LocatePick the largest stage under your control as the bottleneck.
  6. 06
    ShortenSet an hours target per stage and monitor it every month.

The course's 8 lessons: (1) why a single average is misleading, (2) the four stages, (3) measuring stage times, (4) average and 90th-percentile time, (5) the on-target delivery rate, (6) the effect of delay on complaints and returns, (7) finding the bottleneck, (8) the shortening plan and monitoring.

Lesson 1: Why is average delivery time not enough on its own?

In short: The average dissolves a few very late orders into the majority; to see the customer's experience, look at the time of slow orders alongside the average.

In a business that ships 1,000 orders a month, if 900 orders are delivered in 3 days and 100 orders in 12 days, the average comes out to about 3.9 days. The figure looks reasonable; yet 100 customers waited nearly two weeks and most likely contacted you or asked for a return. It is easy to make the average look good, while the promise to the customer is not kept, or is broken, on the slow orders.

That is why measurement uses three numbers together: average time, the 90th-percentile time (the value within which 90% of orders are delivered), and the on-target delivery rate. If you want to ask the same question at the order level, how to measure order fulfillment rate, which measures fulfillment success, will also help; that post looks at whether an order could be shipped, while this one looks at how long delivery took.

Lesson 2: What four stages make up the time from order to delivery?

In short: Confirmation, preparation, handoff, and transit; each stage starts the moment the previous one ends, and their sum gives the time the customer waits.

  • Confirmation. The time from the moment the order arrives until payment and stock are verified and it is taken into preparation. In the example, 6 hours on average.
  • Preparation. The time in which the confirmed order is picked and packed and becomes ready for dispatch. In the example, 30 hours on average.
  • Handoff. The time from the moment the package is ready until it is received by the carrier. In the example, 18 hours on average.
  • Transit. The time from the moment the shipment is received until it reaches the customer. In the example, 42 hours on average.

The total is 6 + 30 + 18 + 42 = 96 hours; 96 ÷ 24 = 4.0 days. The first three stages are in the business's hands, the fourth largely in the carrier's. This distinction matters because the effort to shorten time goes first to the stages in your own hands.

BreakdownBreakdown of the 96-hour average delivery time by stage
  • Confirmation6 hours6.3%
  • Preparation30 hours31.3%
  • Handoff18 hours18.8%
  • Transit42 hours43.8%

The chart shows that transit is the largest share, but shortening it is often not in your hands. Preparation and handoff, however, make up 48 hours of the total, which is half, and depend directly on how you organize your work. To study the internal setup of the preparation stage in detail, see how to do order picking and packing.

Lesson 3: How do you measure stage times?

In short: Write four timestamps on each order: order time, taken into preparation, handed to the carrier, and delivered to the customer; a stage's duration is the difference between two timestamps.

Four pieces of time information are enough for measurement. The order time is already in the system. Taken into preparation is the moment the order is confirmed and reaches the warehouse or packing. Handed to the carrier is the moment the carrier picks up the package; it comes from the shipment tracking record. Delivered to the customer is likewise the delivery time in the shipment tracking record. Stage times are found as follows: confirmation = taken into preparation − order time; preparation and handoff are the differences between the time the package is ready and the time it is handed to the carrier, respectively; transit = delivered to the customer − handed to the carrier.

FormulaFormulas used in measuring delivery time
  1. Confirmation time = Time taken into preparation − Order time
  2. Preparation time = Time the package is ready − Time taken into preparation
  3. Handoff time = Time handed to the carrier − Time the package is ready
  4. Transit time = Time delivered to the customer − Time handed to the carrier
  5. Total delivery time = Confirmation + Preparation + Handoff + Transit

Decide how you will count hours and always use the same method. Calendar hours (weekends included) reflect the customer's actual wait; business-day hours show operational performance more fairly. The example used calendar hours. Whichever you choose, comparison across months is meaningful only with the same method.

If shipment tracking records are missing, you cannot know when a package was actually picked up and delivered; in that case losses and damage also remain invisible. To set up tracking, use the method in how to track lost and damaged shipments. Keeping the customer informed stage by stage also softens the perception of the wait: how to send customers order notifications.

Recommended readingHow do you measure and reduce order sync delay?

Lesson 4: How do you calculate average and 90th-percentile delivery time?

In short: The average is the sum of times divided by the number of orders; the 90th-percentile time is found by sorting times from smallest to largest and taking the value at the ninetieth-percentile position. In the example, the average is 4.0 days and the 90th-percentile time is 6 days.

Let us take a small 10-order example to try by hand. Sorted, the delivery times in days are: 2, 2, 3, 3, 3, 3, 4, 4, 6, 10. The total is 40 and there are 10 orders, so the average is 40 ÷ 10 = 4.0 days. For the 90th-percentile time, look at the value in position 10 × 0.90 = 9; that value is 6. In other words, 90% of orders were delivered within 6 days. The longest time is 10 days.

Rank12345678910
Delivery time (days)22333344610
ComparisonAverage, 90th-percentile, and longest delivery time of the same 10 orders
  1. Average time4.0 days
  2. 90th-percentile time6.0 days
  3. Longest time10.0 days

Prepared with sample values. Calculation: 2 + 2 + 3 + 3 + 3 + 3 + 4 + 4 + 6 + 10 = 40; 40 ÷ 10 = 4.0 days.

The two-day gap between the average and the 90th-percentile time shows how far slow orders drift. When making a promise to the customer, it is safer to rely on the 90th-percentile time, not the average: saying "within 6 days" instead of "4 days for most orders" raises the likelihood that the promise is kept. When working with many orders, applying the same method in a table is enough; as the number of orders grows, the 90th-percentile time becomes more stable.

Lesson 5: How do you calculate the on-target delivery rate?

In short: Divide the orders delivered within the target time by the total number of orders. If the target is 4 days, 8 of the 10 orders in the example meet that limit: 80%.

The on-target rate is the simplest measure that turns delivery time into a "good or bad" answer. You set the target based on the promise you give the customer or your own internal goal. In the example the target is 4 days. The 8 orders with times of 2, 2, 3, 3, 3, 3, 4, 4 met the target; the 2 orders that took 6 and 10 days did not. The on-target rate is 8 ÷ 10 = 80%. Applied to 1,000 orders a month, 800 orders are within target and 200 are outside it.

Takeaways from the exampleFour numbers from the delivery time example
  • 96 hoursthe sum of the stages, an average of 4.0 days
  • 6 daysthe time within which 90% of orders are completed
  • 80%of orders delivered within the 4-day target
  • 56.3%the share of time in the first three stages under the business's control

You can also split the target by product or region group instead of using a single number; setting a longer target for distant regions gives a fair measurement. If you set the target too tight, the rate will always look low and discourage the team; if you set it too loose, the rate will come out high but will not reflect customer satisfaction. To start, take as your target the time you give the customer on the site, on the product page, or in the notification message. For how to monitor this target on the carrier side, see how to measure carrier performance.

Lesson 6: How do late deliveries affect complaints and returns?

In short: Orders outside the target generally have a higher likelihood of complaints and returns; as you raise the on-target rate, the expected number of complaints and returns also falls.

To calculate the effect, take two rates from your own data: the complaint and return rate for orders delivered within the target, and the complaint and return rate for those delivered outside it. In the example, only to demonstrate the method, the complaint rate was taken as 2% within target and 8% outside; the return rate as 8% within target and 12% outside. These are assumptions; your rates may differ.

With an on-target rate of 80%, out of 1,000 orders 800 are within target and 200 are outside. Expected complaints are 800 × 0.02 + 200 × 0.08 = 16 + 16 = 32. Expected returns are 800 × 0.08 + 200 × 0.12 = 64 + 24 = 88. If the on-target rate rises to 90%, 900 orders are within target and 100 outside; expected complaints are 18 + 8 = 26 and expected returns are 72 + 12 = 84. In other words, a ten-point improvement reduces complaints by 6 and returns by 4 per month.

On-target rateOrders within targetOrders outside targetExpected complaintsExpected returns
%707003003892
80% (example)8002003288
%909001002684
ScenarioExpected monthly complaints by on-target rate
  1. 70% on target38 units
  2. 80% on target (example)32 units
  3. 90% on target26 units

The table was calculated for the 70% row with the same method: 700 × 0.02 + 300 × 0.08 = 14 + 24 = 38 complaints, 700 × 0.08 + 300 × 0.12 = 56 + 36 = 92 returns. The figures were chosen only to demonstrate the method; calculate the real effect from your own complaint and return records. To classify complaints by cause, see how to classify and reduce customer complaints; to reduce returns, see how to lower the return rate. Delivery problems also show up in reviews; you can find the review side in how to manage customer reviews and product ratings.

Lesson 7: How do you find the bottleneck in delivery time?

In short: Put the durations of the stages under your control side by side; the stage that takes the most time is the bottleneck. In the example, preparation takes 30 hours, more than half of the first three stages.

The bottleneck is the stage that lengthens total time the most and that you can also change. In the example, transit is the largest stage at 42 hours, but it is in the carrier's hands; to shorten it, you monitor the carrier's performance and, if needed, review the agreement. The stages in your own hands are confirmation 6, preparation 30, and handoff 18 hours; together they total 54 hours. These 54 hours are 56.3% of the total 96 hours. Preparation makes up 30 ÷ 54 = 55.6% of this, so the first place for shortening effort is preparation.

ChartHow the 96-hour time from order to delivery builds up, stage by stage
  1. Confirmation6 hours
  2. Preparation30 hours
  3. Handoff18 hours
  4. Time under the business's control54 hours
  5. Transit42 hours
  6. Total delivery time96 hours

Prepared with sample values. Calculation: 6 + 30 + 18 = 54; 54 + 42 = 96 hours.

To find the cause of the bottleneck, break the stage down internally. If preparation is long, why: are orders processed in batches and waiting for the end of the day, is the stock layout mixed up, is packing concentrated on one person? If handoff is long, why: is the carrier's pickup time being missed, is barcode printing delayed? If confirmation is long, why: is payment verification or manual approval being awaited? You can only ask the question once you have separated the stage; the total figure does not show it. If the workload in the warehouse fluctuates, how to plan warehouse workload is useful for the preparation stage. For the general framework of shipping and logistics management, see the glossary term what is shipping and logistics management in e-commerce.

Recommended readingHow do you do order picking and packing?

Lesson 8: How do you prepare a plan to shorten delivery time?

In short: Set an hours target for each stage under your control, apply the change for a month, and measure again with the same formula. In the example, a 16-hour reduction takes the time from 96 hours to 80.

Sample plan: in confirmation, cut 6 hours to 4 (−2 hours) by confirming orders at frequent intervals during the day; in preparation, bring 30 hours down to 22 (−8 hours) by organizing the picking sequence and the packing station; in handoff, reduce 18 hours to 12 (−6 hours) with an intraday dispatch plan based on pickup time. The total gain is 2 + 8 + 6 = 16 hours. There is no change in the transit stage. The new total is 96 − 16 = 80 hours, about 3.3 days; time is shortened by 16.7%.

StageToday (hours)Target (hours)Gain (hours)
Approval642
Preparation30228
Handoff18126
Don't move42420
Total968016
PlanHours gained per stage in the shortening plan
  1. Preparation8 hours
  2. Handoff6 hours
  3. Confirmation2 hours

The gain estimate is cautious; targets are estimates and may not be met in the first month. What matters is updating the same table at the end of each month and looking for the cause of a missed target within the stage. Seeing orders together with their stage times in one place makes this monitoring easier. To catch orders that get stuck or stall while the plan is running, add the check in how to find stuck marketplace orders to your monthly routine as well.

FrequencyWhat happens
Every weekList the orders outside the target and see in which stage they were delayed
Every monthRecalculate the four stage times, the average, and the 90th-percentile time with the same method
Every monthWrite the on-target rate and the resulting number of complaints and returns into the table
Every quarterReview the target time, the carrier agreement, and dispatch times

What are the most common mistakes in measuring order delivery time?

  1. Looking only at the average. Slow orders get lost inside the average.
  2. Not splitting time into stages. Where the bottleneck is stays invisible.
  3. Counting hours differently each month. If calendar hours and business-day hours are mixed, months cannot be compared.
  4. Not using shipment tracking records. Transit time is written by estimate, and lost or waiting packages go unnoticed.
  5. Setting the target apart from the promise made to the customer. The rate looks good but the customer is not satisfied.
  6. Skipping your own stages while trying to shorten transit. The fastest gain is usually found in preparation and handoff.
  7. Not examining orders outside the target. The records that teach the most are the late ones.

How does NetKasam make delivery time tracking easier?

  • Orders in one panel. Marketplace and e-commerce orders are collected on a single screen; you monitor order times and statuses from the same place (order management).
  • Shipping integration. You send orders to the carrier, generate the barcode, manage regional shipping, and define customer-specific shipping; you see your shipping costs from A to Z (shipping integration).
  • Saved reports. You save the reports you check often, export them to Excel, and prepare your monthly time table with this data (reports).
  • Bookkeeping is free. e-Invoice, customer and supplier accounts, inventory, cash, bank and expense management are free in every plan; see the pricing page for details.

Mini quiz: Test what you have learned

In short: Answer the 5 questions below, then compare with the answer key. 4 or 5 correct shows you have completed the training.

  1. If confirmation is 6, preparation 30, handoff 18, and transit 42 hours, what is the total delivery time in hours and days?
  2. For 10 orders with delivery times of 2, 2, 3, 3, 3, 3, 4, 4, 6, 10 days, what is the 90th-percentile time?
  3. If the target is 4 days, what is the on-target delivery rate for the same 10 orders?
  4. What percentage of total time do the first three stages under the business's control make up?
  5. If 2 hours are gained from confirmation, 8 from preparation, and 6 from handoff, what is the new total time in hours?

Answer key:

  1. 6 + 30 + 18 + 42 = 96 hours; 96 ÷ 24 = 4.0 days.
  2. 10 × 0.90 = the value in position 9: 6 days.
  3. The 8 orders at 4 days and under; 8 ÷ 10 = 80%.
  4. 6 + 30 + 18 = 54; 54 ÷ 96 = %56,3.
  5. 96 − (2 + 8 + 6) = 96 − 16 = 80 hours.

Frequently Asked Questions About Order Delivery Time

How is order delivery time calculated?

It is the time from when the order was placed to when it was delivered to the customer. It equals the sum of the confirmation, preparation, handoff, and transit stages.

What stages does delivery time consist of?

Confirmation, preparation, handoff, and transit. The first three are under the business's control; the last is largely under the carrier's control.

What does 90th-percentile delivery time mean?

It is the value within which 90% of orders are delivered. Times are sorted from smallest to largest and the value at the ninetieth-percentile position is taken; in the example it is 6 days.

Why can average delivery time be misleading?

A small number of very late orders dissolve into the majority and make the average look good. That is why, alongside the average, the 90th-percentile time and the on-target rate should also be tracked.

How is the on-target delivery rate calculated?

The number of orders delivered within the target time is divided by the total number of orders. If 8 out of 10 orders met the target, the rate is 80%.

Should you use calendar hours or business days?

Either can be used; what matters is applying the same method every month. Calendar hours better show the customer's actual wait, while business-day hours better show operational performance.

Where should you start to shorten delivery time?

First measure the stages, then pick the largest stage under the business's control. In the example, it is the preparation stage.

How often should delivery time be measured?

Calculating it monthly is enough; looking at out-of-target orders weekly shows the bottleneck early. Take an interim measurement when the carrier agreement or working schedule changes.

Conclusion: Manage delivery time in stages, not as a single number

The most useful thing you can do today is take a sample of last month's orders and write the four timestamps on each one. Calculate the stage times, the average and 90th-percentile time, and the on-target rate; pick the largest stage under your control and set an hours target for next month.

Bookkeeping Is Now Completely Free

Manage your bookkeeping and e-Invoice operations with NetKasam without paying a thing. Customer and supplier accounts, inventory, collections and more in one panel, completely free.

Start FreeShipping Integration

Read similar articles

19 free tools

Commission, shipping, VAT and profit calculations in your browser, no sign-up needed.

All tools