- What will you be able to do by the end of this training?
- Lesson 1: Why is a warehouse workload plan needed?
- Lesson 2: How is daily capacity per person calculated?
- Lesson 3: How are orders distributed across the week?
- Lesson 4: How many people are needed each day?
- Lesson 5: How do orders pile up with a fixed headcount?
- Lesson 6: How do you compare the cost of the fixed and flexible plans?
- Lesson 7: How do you plan the cutoff time and the peak season?
- Lesson 8: How do you monitor warehouse workload?
- What are the most common mistakes in warehouse workload planning?
- How does NetKasam make warehouse workload planning easier?
- Mini quiz: Test what you have learned
- Conclusion: Build your staffing around the rhythm of your orders
- Frequently Asked Questions About Warehouse Workload Planning
Orders are not distributed evenly across every day of the week. Monday starts with the orders that piled up over the weekend, Tuesday is still busy, and Saturday is quiet. If the same number of people work in the warehouse every day, you end up with a team that falls behind on Monday and stands idle on Saturday. Planning warehouse workload means comparing the daily order count with per-person capacity and adjusting staffing to the workload.
This article is not a narrative but an 8-lesson practical training. We will answer the question how to plan warehouse workload through a sample warehouse that ships 1,200 orders a week: why workload planning is needed, daily capacity per person, the weekday distribution of orders, the number of people needed each day, the backlog a fixed headcount creates, the cost difference of a flexible plan, the daily cutoff time and peak-season plan, and monitoring indicators. At the end there is a mini quiz and an answer key. All figures are sample values chosen to show the method; follow the same steps with your own data.
What will you be able to do by the end of this training?
In short: You will calculate per-person capacity, work out the distribution of orders across days, find the number of people needed each day and compare the cost of the fixed and flexible plans.
- 01MeasureFind the time it takes to pick and pack one order.
- 02Find the capacityCalculate the daily order capacity per person.
- 03DistributeSpread the weekly orders across the days.
- 04Set the staffingFind the number of people needed for each day.
- 05ComparePut the cost of the fixed and flexible plans side by side.
- 06MonitorTrack capacity utilization and the orders carried over.
The 8 lessons of the training: (1) why a workload plan is needed, (2) daily capacity per person, (3) the weekday distribution of orders, (4) the number of people needed each day, (5) orders carried over with a fixed headcount, (6) the cost of the fixed and flexible plans, (7) the cutoff time and peak-season plan, (8) monitoring indicators.
Lesson 1: Why is a warehouse workload plan needed?
In short: Without a plan, orders are delayed on busy days and the team stands idle on quiet days. Both are costs: one is lost customers, the other wasted wages.
A delay on a busy day has a chain effect: a late order is added to the next day's load, and the next day runs late too. Orders that miss the shipping cutoff time and go out the following day break the customer's delivery expectation. To measure handover-to-carrier time, see the article how to measure and shorten time to ship. On a quiet day, a waiting team is of no use; wages are fixed, and every unused person-day is wasted.
A workload plan answers two questions: how many people are needed today, and where can we shift surplus capacity? The plan should be built on past order data, not on gut feeling. Use your order management screen as the source of order data; for managing orders from different channels together, see the article how to do order management in e-commerce.
Lesson 2: How is daily capacity per person calculated?
In short: Per-person capacity is found by dividing daily productive working time by the average time it takes to pick and pack one order.
- Daily capacity per person = Daily productive time (minutes) ÷ Time per order (minutes)
- Number of people needed = Daily orders ÷ Daily capacity per person
- Capacity utilization = Orders shipped ÷ (Number of people × Capacity per person)
In the sample warehouse, an employee works productively 8 hours, or 480 minutes, a day. Picking, checking and packing one order takes an average of 8 minutes. Daily capacity per person is 480 ÷ 8 = 60 orders. The time per order should be found by measuring: picking sample orders for a week and counting the time is enough. We described the picking layout and packing flow that affect this time in the article how to pick and pack orders. Manually entered orders lengthen the time; for the cost of that, see the article how to calculate the cost of manual order processing.
Productive time is not the same as shift time: it is what remains after lunch breaks, pauses and changeover time are deducted. If an 8-hour shift has 6.5 productive hours, capacity drops to 390 ÷ 8 ≈ 49 orders; so, as in the example, verify the productive hours even for 8 hours before using them.
Lesson 3: How are orders distributed across the week?
In short: In the sample warehouse, of the weekly 1,200 orders, the busiest day is Monday at 25% and the quietest day is Saturday at 10%.
| Day | Order | Weekly share |
|---|---|---|
| Monday | 300 | %25,0 |
| Tuesday | 240 | %20,0 |
| Wednesday | 180 | %15,0 |
| Thursday | 180 | %15,0 |
| Friday | 180 | %15,0 |
| Saturday | 120 | %10,0 |
| Total | 1.200 | %100 |
- Monday₺30025%
- Tuesday₺24020%
- Wednesday₺18015%
- Thursday₺18015%
- Friday₺18015%
- Saturday₺12010%
Prepared with sample values. The days add up to 1,200 orders.
Monday and Tuesday carry 45% of total orders. The carry-over of orders placed over the weekend to Monday is decisive in this table: orders that arrive between Saturday evening and Monday morning pile up on the first day. Work out your own distribution by averaging the daily order counts of the last 8-12 weeks; do not rely on a single week. To forecast next week's total order count, use the method in the article how to make a sales forecast and multiply the forecast by this daily distribution.
Lesson 4: How many people are needed each day?
In short: The daily orders are divided by the capacity of 60 orders per person. In the example, 5 people are needed on Monday, 4 on Tuesday, 3 on Wednesday, Thursday and Friday, and 2 on Saturday.
| Day | Order | Account | People needed |
|---|---|---|---|
| Monday | 300 | 300 ÷ 60 | 5 |
| Tuesday | 240 | 240 ÷ 60 | 4 |
| Wednesday | 180 | 180 ÷ 60 | 3 |
| Thursday | 180 | 180 ÷ 60 | 3 |
| Friday | 180 | 180 ÷ 60 | 3 |
| Saturday | 120 | 120 ÷ 60 | 2 |
| Total person-days | 1.200 | 20 |
The weekly total is 5 + 4 + 3 + 3 + 3 + 2 = 20 person-days. If the order count does not divide evenly by capacity, round up; for example, for 330 orders, 330 ÷ 60 = 5.5 → plan for 6 people or call in half-day support. Once you decide who will work on which task each day, see the article how to set up user permissions for defining authorities and duties. To calculate staff cost, you can use the article how to calculate staff cost.
Lesson 5: How do orders pile up with a fixed headcount?
In short: If 3 people work every day, daily capacity is 180. The Monday and Tuesday peak is carried over and 120 orders are left behind at the weekend.
With a fixed team of 3, daily capacity is 3 × 60 = 180 orders. The orders carried over at day end are calculated as: carried over from the previous day + that day's orders − capacity (zero if negative).
| Day | Carried over (opening) | Incoming | Total work | Shipped (up to 180) | Carried over at day end |
|---|---|---|---|---|---|
| Monday | 0 | 300 | 300 | 180 | 120 |
| Tuesday | 120 | 240 | 360 | 180 | 180 |
| Wednesday | 180 | 180 | 360 | 180 | 180 |
| Thursday | 180 | 180 | 360 | 180 | 180 |
| Friday | 180 | 180 | 360 | 180 | 180 |
| Saturday | 180 | 120 | 300 | 180 | 120 |
- Monday120 orders
- Tuesday180 orders
- Wednesday180 orders
- Thursday180 orders
- Friday180 orders
- Saturday120 orders
Prepared with sample values. Carried over = previous carry-over + incoming − 180 capacity.
At the weekend 120 orders are left behind and Monday starts with them; that is, weekly capacity is 6 × 180 = 1,080 orders and does not cover 120 of the 1,200 orders. A permanent delay builds up in the system: from Wednesday to Friday, a stack of 180 orders goes out a day later every day. Late shipping increases cancellations and customer complaints; when promising delivery times, also see the capacity check in the article how to prepare for a busy campaign period.
Lesson 6: How do you compare the cost of the fixed and flexible plans?
In short: Running 4 people every day ships orders completely but creates ₺4,800 of idle capacity per week. The workload-based plan ships the same orders in 20 person-days.
With a fixed team of 4, daily capacity is 240. With 300 orders on Monday, 60 orders are carried over; Tuesday 240 + 60 = 300 − 240 = 60 carried over; Wednesday 180 + 60 = 240 − 240 = 0; that is, the delay lasts until Wednesday and then clears. Weekly person-days are 4 × 6 = 24. If the cost per person-day is taken as ₺1,200, the fixed plan is 24 × 1,200 = ₺28,800 and the flexible plan is 20 × 1,200 = ₺24,000.
- Fixed plan of 4 (24 person-days × ₺1,200)₺28,800
- Idle capacity (4 person-days)−₺4,800
- Flexible plan (20 person-days × ₺1,200)₺24,000
Prepared with sample values. Total: 28,800 − 4,800 = ₺24,000.
| Plan | Weekly person-days | Cost | Capacity utilization | Carried over at weekend |
|---|---|---|---|---|
| Fixed 3 people | 18 | 21.600 ₺ | 111.1% (not enough) | 120 orders |
| Fixed 4 people | 24 | 28.800 ₺ | %83,3 | 0 |
| Flexible (5-4-3-3-3-2) | 20 | 24.000 ₺ | %100 | 0 |
With a fixed team of 3, capacity utilization is 1,200 ÷ 1,080 = 111.1%; because capacity is not enough, orders pile up and 120 are carried over. With a fixed team of 4, it is 1,200 ÷ 1,440 = 83.3%: capacity for 240 orders sits idle, which equals 4 person-days. In the flexible plan, utilization is 100%, but there is no margin: one person calling in sick or a 10% rise in orders immediately creates a backlog. So in practice a small safety margin is added to the flexible plan; how to calculate that margin follows the same logic as in the article how to calculate safety stock.
To apply the flexible plan, part of the staff is planned as full-time and part as day-based support: for example, 3 people fixed, 2 people on Monday and 1 person on Tuesday as support. If weekly orders increase, support days are added. We covered employee expenses and advance and overtime calculations in the article how to track staff advances and overtime.
Lesson 7: How do you plan the cutoff time and the peak season?
In short: Set a cutoff time so orders ship the same day, and plan the peak season by multiplying the Monday baseline.
The cutoff time is the last time orders are accepted for shipping that day: for example, an order placed before 14.00 is handed to the carrier the same day, and later orders go the next day. The cutoff time should be set according to workload: because Monday is busy, moving the cutoff to 12.00 and keeping it at 15.00 on other days can split the order backlog. The carrier's daily pickup time is the upper limit of this rule; for the shipping rule, see the article how to create region-based shipping rules.
In the peak season, multiply the Monday baseline by the order increase. If orders rise 50% during a campaign week, Monday becomes 300 × 1.5 = 450 orders and 450 ÷ 60 = 7.5 → 8 people are needed. This figure is used to call in support before the campaign calendar. To calculate a campaign's order load in advance, carry the target order count from the article how to set up a store campaign into this table. If you have more than one warehouse, you can distribute the load among them; for that method, see the article how to route orders across multiple warehouses.
Recommended readingHow to Do Order Picking and Packing?Lesson 8: How do you monitor warehouse workload?
In short: Monitor five indicators weekly: daily orders, capacity utilization, orders carried over at day end, time per order and same-day shipping rate.
| Indicator | How it is calculated | Sample value |
|---|---|---|
| Daily orders | Number of orders received during the day | 120 – 300 |
| Capacity utilization | Orders shipped ÷ Capacity | 83.3% (fixed 4 people) |
| Carried over at day end | Open orders not shipped | Target: 0 |
| Time per order | Picking + checking + packing minutes | 8 min |
| Same-day shipping rate | Orders received by the cutoff time and shipped the same day ÷ Orders received | Target: 98%+ |
- 60daily order capacity per person
- 5 – 2range of people needed per day
- 120orders carried over at the weekend with a fixed team of 3
- ₺4,800weekly saving of the flexible plan
Time per order is the source of capacity; a new product group, a packaging change or a new channel can lengthen it. If the time rises from 8 minutes to 9 minutes, per-person capacity falls to 480 ÷ 9 ≈ 53 orders and one more person may be needed for the same load; so re-measure the time every three months. To add the indicator table to the weekly report, use the layout in the article how to prepare a weekly management report. To separately measure the share of missing or late orders, see the article how to measure order fulfillment rate.
Recommended ReadingHow Do You Calculate the Cost of Stockouts? A Course on Lost Sales, Indirect Loss, Loss by Product Class, the Extra Stock Decision, Early Warning Rules and Limiting LossesWhat are the most common mistakes in warehouse workload planning?
- Putting the same team on every day. Orders pile up on Monday and the team stands idle on Saturday.
- Counting shift time as capacity. Productive time is shorter than the shift; capacity is overstated.
- Guessing the time per order. A capacity calculation without measurement does not come out realistic.
- Relying on a single week's data. The distribution should be derived from an 8-12 week average.
- Not tracking carried-over orders. The backlog is only noticed when customers complain.
- Building the flexible plan without a margin. A single absence creates a delay.
- Not calculating the peak season in advance. Calling in support on campaign day is too late.
How does NetKasam make warehouse workload planning easier?
- Single-screen order management. You see orders from different channels together and monitor the daily order count (order management).
- User and employee management. You define your employees and their permissions and see transactions by user (user and employee management).
- Branch and warehouse-based work. You track inventory and orders separately by warehouse (branch and warehouse management).
- Inventory movements. You verify the daily volume with outgoing movements (inventory management).
- Bulk invoicing. You reduce the pre-shipment load by invoicing orders in bulk.
- Saved reports. You save the weekly report and export it to Excel (reports).
- Bookkeeping is free. e-Invoice, customer and supplier accounts, inventory, cash, bank and expense management are free in every plan; see the pricing page for details.
Mini quiz: Test what you have learned
In short: Answer the 5 questions below, then compare with the answer key. 4 or 5 correct shows you have completed the training.
- If daily productive time is 480 minutes and time per order is 8 minutes, what is the daily capacity per person?
- If Monday has 300 orders and per-person capacity is 60, how many people are needed?
- What is the daily capacity with a fixed team of 3?
- If the flexible plan is 20 person-days a week and the cost per person-day is ₺1,200, what is the weekly cost?
- With a fixed team of 4 and 1,200 weekly orders, what is the capacity utilization percentage (6 days, daily capacity 240)?
Answer key:
- 480 ÷ 8 = 60 orders.
- 300 ÷ 60 = 5 people.
- 3 × 60 = 180 orders.
- 20 × 1.200 = 24.000 ₺.
- 1.200 ÷ (6 × 240 = 1.440) = %83,3.
Frequently Asked Questions About Warehouse Workload Planning
What is a warehouse workload plan?
It is the exercise of comparing daily order counts with per-person capacity to determine the number of people needed each day.
How is daily capacity per person calculated?
The productive working time per day is divided by the time it takes to pick and pack one order. For 480 minutes and an 8-minute order, the capacity is 60.
How do you find the number of people needed?
The daily order count is divided by the per-person capacity and rounded up if needed.
Why does a fixed headcount cause problems?
Because orders are not spread evenly across days, a backlog builds up on busy days and idle capacity appears on quiet days.
How is a flexible plan applied?
The core staff stays fixed, and support workers or shifts are added on busy days. Staffing is set according to the daily order distribution.
Why does the cutoff time matter?
It determines which orders ship the same day. On busy days, an earlier cutoff time reduces order backlog.
How many people are needed in the peak season?
The busiest day of a normal week is multiplied by the expected increase rate and divided by the per-person capacity. With a 50% increase, 8 people are needed for 450 orders.
How often should warehouse indicators be monitored?
Weekly. The orders carried over at day end are monitored every evening, because a backlog can grow within a few days.
Conclusion: Build your staffing around the rhythm of your orders
The most useful thing you can do today is to average the daily order counts of the last eight weeks by day of the week and measure the picking and packing time of one order. The next step is to calculate per-person capacity, write down the number of people needed each day and start monitoring the orders carried over at day end. Shipping the same orders with fewer person-days and bringing the late order count close to zero is possible by fitting your staffing to the rhythm.