How Do You Measure and Shorten Time to Ship? A Guide to Time Distribution, the Cost of Delay, Causes of Delay, the Impact of Rating Thresholds and Improvement
How do you measure and shorten time to ship? Time distribution, the cancellation and rating cost of delays, causes of delay and the threshold effect: an 8-lesson guide with examples.
Contents 14 sections
- What will you be able to do by the end of this training?
- Lesson 1: From where to where is time to ship measured?
- Lesson 2: Which formulas calculate the cost of delays?
- Lesson 3: Why is the average time misleading?
- Lesson 4: What is the monthly cost of delays?
- Lesson 5: What causes delays?
- Lesson 6: How much does each improvement gain, and why does the threshold matter?
- Lesson 7: What are the practical rules that prevent delays?
- Lesson 8: How do you monitor time to ship?
- What are the most common mistakes with time to ship?
- How does NetKasam shorten time to ship?
- Mini quiz: Test what you have learned
- Conclusion: This week, work out your late rate and your biggest cause of delay
- Frequently Asked Questions About Time to Ship
You receive 5,000 orders a month and your average time to ship is 18.8 hours. Since the marketplace requires 24 hours, everything looks fine. Yet in the same month, 1,100 orders exceed the target, cancellations rise and your seller rating quietly drops. It is very common for the problem to hide in the tail, that is, in the latest-shipped orders, while the average looks good; that is why time to ship is measured not with a single number but with a distribution.
This article is not an overview but an 8-lesson hands-on training. We will answer the question how do you measure and shorten time to ship using a month of 5,000 orders: from where to where the time should be measured, why the average is misleading, the cost of delays through cancellations and ratings, the causes of delay, how much each improvement gains, the effect of the rating threshold and the monitoring indicators. At the end there is a mini quiz and an answer key. A shipped package getting lost or damaged in transit is a separate topic; we covered it in the article how to track lost and damaged shipments. This article focuses on the time before the package leaves the warehouse.
What will you be able to do by the end of this training?
In short: You will measure time to ship from the right points, map out its distribution, calculate the monthly cost of delays, separate the causes of delay and evaluate improvements together with the threshold effect.
- 01MeasureRecord the time from confirmation to carrier handover.
- 02DistributeSplit the times into ranges; do not rely on the average.
- 03Cost itFind the cancellation and rating cost of late orders.
- 04Find the causeSeparate delays by cause.
- 05ImproveChoose fixes aimed at getting below the threshold.
- 06MonitorTrack the late rate weekly.
The training's 8 lessons: (1) defining time to ship, (2) formulas, (3) the average fallacy and the distribution, (4) the cost of delays, (5) causes of delay, (6) improvements and the threshold effect, (7) practical rules, (8) monitoring indicators.
Lesson 1: From where to where is time to ship measured?
In short: Time to ship is the time from the moment the order is confirmed until the package is handed to the carrier. The starting point is not the moment the order arrives but the moment it is ready to be processed.
The time consists not of a single step but of five consecutive steps. To see which step is taking longer, you need to record the time of each step separately.
| Step | What happens | Typical cause of longer times |
|---|---|---|
| 1. Confirmation | The order lands in the panel and is confirmed | Noticing the order late, waiting for payment approval |
| 2. Invoice and label | The invoice is issued and the shipping label is prepared | Processing each order one by one |
| 3. Picking | Products are found on the shelf | Unclear inventory location, wrong shelf |
| 4. Packing | The product is packed and the label is attached | Capacity, lack of materials |
| 5. Handover | The package is handed to the carrier | The carrier's pickup time is missed |
Sample business: an e-commerce business that receives about 5,000 orders a month, sells on marketplaces and its own site, and ships orders from a single warehouse. Marketplaces have different time rules and scoring methods; the 24-hour target and 10% threshold in this article are sample assumptions. Use the rule in your own marketplace panel. For managing orders end to end, see the article how to manage orders in e-commerce, and for the picking and packing steps, see the article how to do order picking and packing.
Lesson 2: Which formulas calculate the cost of delays?
In short: The late rate is the number of late orders divided by total orders. The cost arises in two ways: additional cancellations on late orders and the lost sales that occur when the late rate exceeds the threshold.
- Late rate (%) = Orders exceeding the target ÷ Total orders × 100
- Additional cancellation cost = Late orders × (Late cancellation rate − On-time cancellation rate) × Loss per cancellation
- Rating loss = If the late rate exceeds the threshold, Total orders × Lost sales rate × Contribution per order
- Monthly cost of delays = Additional cancellation cost + Rating loss
Prepared with sample values. Loss per cancellation is the sum of the lost contribution and the cancellation processing cost.
Assumptions used in the example: contribution per order ₺160; cancellation processing and customer communication cost ₺20, so the loss per cancellation is ₺180; the cancellation rate is 1% for orders shipped on time and 12% for orders shipped late; if the late rate exceeds 10%, about 3% of sales are lost. Derive these rates from your own history, your cancellation reason records and the weeks in which you saw your rating change; the figures in the example only show how the calculation is set up. For the logic of the contribution calculation, see the article how to calculate profit margin.
Lesson 3: Why is the average time misleading?
In short: The average mixes fast orders with slow orders. For an accurate picture, you split the time into ranges and look at the share of orders that exceed the target.
The time to ship of 5,000 monthly orders is distributed across ranges as follows:
| Time range | Order | Share | Against target |
|---|---|---|---|
| 0–12 hours | 2.000 | %40 | On time |
| 12–24 hours | 1.900 | %38 | On time |
| 24–48 hours | 750 | %15 | Late |
| Over 48 hours | 350 | %7 | Late |
| Total | 5.000 | %100 | 1,100 late (22%) |
- 0–12 hours2,000 orders
- 12–24 hours1,900 orders
- 24–48 hours750 orders
- Over 48 hours350 orders
Prepared with sample values. The target is taken as 24 hours.
Let's calculate the average using the midpoints of the ranges (6, 18, 36 and 60 hours): (2,000 × 6 + 1,900 × 18 + 750 × 36 + 350 × 60) ÷ 5,000 = 94,200 ÷ 5,000 = 18.84 hours. The report says "average 18.8 hours, below target" and the problem stays hidden. Yet one in every five orders exceeded the target. Marketplace ratings usually look not at the average but at the share of orders that exceed the target; that is why the number you need to monitor is not 18.8 but 22%.
Lesson 4: What is the monthly cost of delays?
In short: Cancellations rise on orders shipped late; when the late rate exceeds the threshold, sales also fall. In the example, the two items total ₺45,780 a month.
| Item | Account | Amount |
|---|---|---|
| Orders shipped on time | 3,900 orders, 1% cancellation = 39 | – |
| Orders shipped late | 1,100 orders, 12% cancellation = 132 | – |
| Cancellations if all were on time | 5.000 × %1 = 50 | – |
| Additional cancellations | 171 − 50 = 121 cancellations × ₺180 | 21.780 ₺ |
| Rating loss | Late rate 22% > 10% threshold; 5,000 × 3% = 150 orders × ₺160 | 24.000 ₺ |
| Monthly cost of delays | 45.780 ₺ |
We can do the same calculation per late order: the additional cancellation probability is 11% (12% − 1%), the loss per cancellation is ₺180, so the additional cost per late order is ₺19.80. 1,100 late orders × ₺19.80 = ₺21,780. This is the most visible part of the delay. The larger item is the invisible rating loss: at ₺24,000, it is even higher than the cancellation cost. Its yearly equivalent is 45,780 × 12 = ₺549,360, and it never appears as a line called "delay cost" on any invoice; it is scattered across the profit statement as lower sales and higher cancellations.
Note: the rating loss rate varies by marketplace, and 3% is a sample assumption. If there is no threshold, take this item as zero; the calculation still works with the additional cancellation cost. For the cost of cancellations themselves, see the article how to cancel an order.
Recommended readingHow Do You Lower the Return Rate?Lesson 5: What causes delays?
In short: Separating late orders by cause shows how many orders each fix will save. Record the reason for each late order; do not rely on guesses.
In the example, the causes of the 1,100 late orders are distributed as follows:
- Finding the product on the shelf₺34030.9%
- Invoice and label preparation₺30027.3%
- Packing capacity₺24021.8%
- Missing the carrier pickup time₺22020%
Prepared with sample values.
| Reason | Late orders | Share | Root cause |
|---|---|---|---|
| Finding the product on the shelf | 340 | %30,9 | No shelf location record, the same product in multiple places |
| Invoice and label preparation | 300 | %27,3 | Processing each order separately |
| Packing capacity | 240 | %21,8 | A single shift on busy days |
| Carrier pickup time | 220 | %20,0 | One pickup a day; orders that arrive in the afternoon are left for the next day |
| Total | 1.100 | %100 |
What matters here is that the causes require different solutions: invoice and label delays are a process and tool problem, packing delays are a capacity problem, and the carrier pickup time is something to arrange with the carrier. Rather than trying to solve them all with a single solution, you need to choose a separate fix for each cause. For shelf organization and picking errors, see the article how to do an inventory count, and for the shipping side, see the article how shipping integration works and how to choose one.
Lesson 6: How much does each improvement gain, and why does the threshold matter?
In short: Each improvement partially solves a particular cause. The real difference comes when the late rate drops below the threshold, because the rating loss disappears all at once.
Four fixes and the number of late orders each one saves:
| Correction | Effect | Late orders saved | Cancellation savings (₺19.80) |
|---|---|---|---|
| Preparing invoices and labels in bulk | 80% of this cause is solved | 240 | 4.752 ₺ |
| Shelf location records and picking lists | 50% of this cause is solved | 170 | 3.366 ₺ |
| A second carrier pickup each day | 50% of this cause is solved | 110 | 2.178 ₺ |
| An extra packing shift on busy days | 50% of this cause is solved | 120 | 2.376 ₺ |
| Total | 640 | 12.672 ₺ |
After the fixes, the number of late orders becomes 1,100 − 640 = 460; the late rate is 460 ÷ 5,000 = 9.2%, below the 10% threshold. At this point, the rating loss of ₺24,000 drops to zero all at once. The monthly cost of delays falls from ₺45,780 to ₺9,108.
- Starting cost of delays₺45,780
- Preparing invoices and labels in bulk−₺4,752
- Shelf location records and picking lists−₺3,366
- Second carrier pickup−₺2,178
- Extra packing shift−₺2,376
- Late rate dropping below the threshold−₺24,000
- Remaining cost of delays₺9,108
Prepared with sample values. Total: 45,780 − 4,752 − 3,366 − 2,178 − 2,376 − 24,000 = ₺9,108.
The extra packing shift costs ₺14,000 a month and, viewed on its own, provides only ₺2,376 in cancellation savings; at first glance it seems to make no sense. Consider it together with the threshold effect. Without the shift, 580 late orders remain, the rate is 11.6% and the threshold is still exceeded: cancellation cost 580 × 19.80 = ₺11,484, rating loss ₺24,000, total ₺35,484. With the shift, the total is 9,108 + 14,000 = ₺23,108. The shift brings a net gain of ₺12,376 a month, because it is the final step that brings the rate below the threshold. This is the most common mistake in threshold-based scoring systems: evaluating each fix by its own direct return and failing to account for the return of getting below the threshold.
The other three fixes require no extra cost (bulk preparation is done within the system, shelf records are a one-time effort, and the second pickup is arranged in the shipping agreement). Net monthly gain: 45,780 − 23,108 = ₺22,672. Note: the cost of the extra shift and the rates are sample assumptions; multiply with your own figures. To work out this table ahead of a busy period, see the article how to prepare for a busy campaign period.
Lesson 7: What are the practical rules that prevent delays?
In short: The trio of a cutoff time, a priority order and an alert rule catches delays before they become a problem.
| Rule | How to apply it | Reason |
|---|---|---|
| Cutoff time | Set the latest order time that must be ready before the carrier pickup time | Every order makes the carrier's daily pickup |
| Priority order | Move orders with little delivery time left to the front; sort by time remaining, not oldest to newest | Targets are most often missed on orders left to the last hour |
| Alert | List orders that have reached 75% of the target (hour 18 in the example) and are not yet packed | Intervening before the delay happens |
| Daily closing | At the end of the day, count the orders about to exceed the target | Seeing orders that spill over to the next day |
| Customer notice | Notify the customer in advance about an order that will be late | Lowers the likelihood of cancellation |
Most of these rules require seeing orders on a single screen. In NetKasam, marketplace and e-commerce orders are gathered in one panel; you can filter orders and invoice, print and ship them in bulk. Along with bulk printing and invoicing, smart sorting and staff assignment functions speed up warehouse processes. If you want, invoicing happens automatically the moment an order lands in the system, so the invoice and label step drops off the waiting list. For the bulk invoicing flow, see the article how to invoice orders in bulk, and for customer notifications, see the article how to send order notifications to customers.
Lesson 8: How do you monitor time to ship?
In short: Track four indicators weekly: the late rate, the time distribution, the cause of late orders and the cancellation rate on late orders.
| Indicator | Getting started | Target | How it is calculated |
|---|---|---|---|
| Late rate | %22 | Below 10% (9.2% in the example) | Orders exceeding the target ÷ Total orders |
| Orders over 48 hours | 350 | Close to zero | Order count in the longest range |
| Cancellation rate on late orders | %12 | Below 5% | Cancellations on late orders ÷ Late orders |
| Monthly cost of delays | 45.780 ₺ | 9.108 ₺ | Additional cancellations + rating loss |
- 18.8 hoursaverage time, which looks below target
- 22%share of orders exceeding the target nonetheless
- ₺45,780monthly cost of delays
- ₺22,672net monthly gain after four fixes
If the late rate is falling but your rating is not changing, consider that you may have the threshold wrong or that your rating is dropping because of another item (cancellations, returns). If the number of orders over 48 hours is not falling, the problem is not capacity but forgotten or stalled orders; in that case, tighten the time-remaining alert. For a weekly view, you can add these four indicators to the table in the article how to prepare a weekly management report. If you ship from more than one warehouse, also break the time down by warehouse; for routing rules, see the article how to route orders across multiple warehouses.
Recommended ReadingHow to Sync Marketplace Inventory?What are the most common mistakes with time to ship?
- Looking only at the average. Orders that exceed the target get lost in the average.
- Starting the clock at the wrong point. Counting from packing instead of order confirmation makes the delay look smaller.
- Not recording the cause. Late orders are counted, but the cause is unknown.
- Not knowing the threshold. Being very close to the threshold and missing the rating you could gain with a small fix.
- Evaluating fixes only by their direct return. Failing to account for the threshold effect.
- Not accounting for busy periods. Capacity that is enough in a normal month is not enough in a campaign week.
- Not informing the customer. An order that will be late quietly turns into a cancellation.
How does NetKasam shorten time to ship?
- Single panel. You see marketplace and e-commerce orders on a single screen and don't miss any order (order management).
- Bulk actions. You filter orders and invoice, print and ship them in bulk.
- Automatic invoicing. If you want, the invoice is issued the moment the order lands in the system; the e-Invoice image link is automatically sent to the marketplace (marketplace integration).
- Carrier transfer. Orders ready to ship are automatically sent to the carrier through the shipping integration (shipping integration).
- Sorting and assignment. Smart sorting and staff assignment functions speed up the warehouse process.
- Inventory alerts. You get notified at critical inventory levels and reduce delays caused by shelf and inventory issues (inventory management).
- Bookkeeping is free. e-Invoice, customer and supplier accounts, inventory, cash, bank and expense management are free in every plan; for marketplace integration plans, see the pricing page.
Mini quiz: Test what you have learned
In short: Answer the 5 questions below, then compare with the answer key. 4 or 5 correct shows you have completed the training.
- The average time to ship is 18 hours and the target is 24 hours. Why could there still be a problem?
- 1,100 of 5,000 orders are late. What is the late rate?
- The cancellation rate is 12% on late orders and 1% on on-time orders; the loss per cancellation is ₺180. What is the additional cancellation cost of 1,100 late orders?
- After the fixes, 460 late orders remain and the threshold is 10%. Is the threshold exceeded?
- If an extra shift costing ₺14,000 provides only ₺2,376 in cancellation savings, why could it still make sense?
Answer key:
- The average hides orders that exceed the target; the distribution may have a tail beyond the target, and ratings usually look not at the average but at the late rate.
- 1.100 ÷ 5.000 = %22.
- Additional cancellations 11%; 1,100 × 0.11 = 121 cancellations; 121 × 180 = ₺21,780.
- 460 ÷ 5,000 = 9.2%; it is below the threshold, so the rating loss disappears.
- If the shift brings the late rate below the threshold, it also eliminates the ₺24,000 rating loss; in the example, the shift brings a net gain of ₺12,376 a month.
Frequently Asked Questions About Time to Ship
How do you measure time to ship?
It is the time from the moment the order is confirmed until the package is handed to the carrier. Recording the invoice, picking, packing and handover steps separately shows which step is taking longer.
Why is the average time not enough?
The average mixes fast orders with slow ones. You need to look at the share of orders that exceed the target and at the time distribution.
How do you calculate the cost of delays?
You multiply the additional cancellation rate on late orders by the loss per cancellation; if the late rate exceeds the marketplace threshold, you also add the lost sales.
What should the late rate be?
Below the marketplace's threshold. The threshold and the scoring method vary by marketplace; go by the rule in your own seller panel.
How do you find the causes of delays?
Record the cause of each late order: finding the product, invoice and label, packing capacity, carrier pickup time. The distribution shows which fix should come first.
When does an extra shift or extra staff make sense?
Compare the cost with the direct cancellation savings as well as the threshold effect. If it brings the late rate below the threshold, it also eliminates the rating loss.
Why does the carrier pickup time matter?
If there is only one pickup a day, orders that come in during the afternoon are left for the next day. A second pickup or an earlier cutoff time reduces this loss.
How does NetKasam help with time to ship?
It gathers orders in a single panel, offers bulk invoicing and printing, can invoice automatically if you want, and sends orders to the carrier through the shipping integration; bookkeeping is free.
Conclusion: This week, work out your late rate and your biggest cause of delay
The most useful thing you can do today is find two numbers: your share of orders that exceeded the target over the last four weeks and the biggest cause of late orders. The first shows how close you are to the threshold; the second shows which fix to start with. The next step is to apply the fix that saves the most orders and track the late rate in the same table every week.